Level Resources Without Extending The End Date

This article explains how resources can be level without extending the end date in Project 2010.
  • 2110

Introduction

If you want to automatically level resources without moving the project end date, level only within available slack option can be used. Process for level resources without extending the end date is given below.

Step 1

Click on the Resources tab.

 select-resource-tab-in-project 2010.jpg

Step 2

Then click on the Leveling Options button.

 select-leveling-option-in-project 2010.jpg

Step 3

Check the Level Only Within Available Slack Option.

 check-slack-option-in-project 2010.jpg

Step 4

Mark the Level Only Within Available Slack Option, if it is not selected.

 mark-slack-option-in-project 2010.jpg

Step 5

Click on OK button.

 confirm-slack-option-in-project 2010.jpg

Step 6

Then click the Level All button.

 level-all-resources-in-project 2010.jpg