How To Link Tasks In Project 2010
This article shows how to link tasks in Project 2010.
Introduction
Process to link tasks in the Gantt Chart view in Project 2010 is given below.
Step 1
On the View tab, in the Task Views group, click Gantt Chart.
Step 2
In the Task Name field, select two or more tasks you want to link, in the order you want to link them.
1. To select tasks that are next to one another, hold down SHIFT and click the first and last task that you want to link.
2. To select tasks that are not next to one another, hold down CTRL and click the tasks that you want to link.
Step 3
On the Task tab, in the Schedule group, click the Link Tasks button.
Project 2010 automatically creates a finish-to-start link. You can also change this task link to start-to-start, finish-to-finish or start-to-finish.